Find the full zone code in Navigate Newmarket
Search the street address and enable both planning layers, Comprehensive Zoning By-law 2010-40 and Urban Centres Zoning By-law 2019-06. Select the property to read its code. A suffix matters. For example, a code ending in an exception number directs you to additional provisions in section 8. Read those alongside the permitted uses for the underlying zone. The Town directs Oak Ridges Moraine zoning inquiries to Planning. The map can also help flag a heritage listing or conservation authority involvement.
From zoning review to a permit file
For a deck, show the location and dimensions clearly enough for the Town to review the proposal against the property lines. Keep the zoning review result with the project documents. Newmarket charges for this preliminary review and says it deducts that fee from the subsequent building permit fee. Complete the forms with the owner’s and applicant’s contact details, then submit the documents through the Development Portal.
How should the drawings be delivered?
Export scaled construction sheets as unlocked black-and-white PDFs. Put the submission date in the title block. File-sharing links, ZIP archives and JPEGs do not meet Newmarket’s submission instructions. Watch for both the automatic receipt and the technician’s follow-up about fees. Respond to any examiner questions using the same project reference. After issuance, the Town asks applicants to contact its inspections team two days ahead of the requested inspection.
What belongs in a Newmarket deck zoning review?
Start with two outlines on a survey or reliable site plan: the house as it stands and the deck as you intend to build it. Mark where the stairs land. Newmarket’s deck information sheet asks for the zone and any suffix, whether the property is a corner lot, and distances to the side and rear property lines. A setback measured from the house wall tells staff something different from one measured from the nearest part of the proposed deck. Identify the endpoints of each dimension.
The Town’s guide calls for front and side elevations with the preliminary zoning submission. Include the ground line, door threshold, platform level and stairs. On a sloping lot, record the grade on each relevant side. Two platforms with identical footprints can sit at very different heights above the yard. If the deck changes level or wraps around a corner, use an additional view wherever the first two leave the stairs or landing unclear.
How do those drawings become construction plans?
Once the zoning dimensions are settled, use that same outline to prepare the framing plan. The builder needs to see the direction of the joists, where beams bear, the locations of posts and footings, and how the deck meets the house. If part of the existing deck will stay, identify it explicitly. Label existing framing that still needs confirmation rather than drawing it as though someone had already inspected it.
Newmarket’s deck guide describes a footing inspection while the excavations are visible and a final inspection when the work is complete. Use the inspection stages on the issued permit to agree with the contractor when to call. If moving a post, increasing the deck width or changing the stairs becomes necessary, ask the inspector about a revision before building the change. Keep the final approved layout with the house records so a later owner can identify exactly what was permitted.
Newmarket permit questions
Can I start the deck while Newmarket reviews zoning?
Wait for the required building permit before starting construction. The preliminary review addresses zoning. Keep its outcome and the accepted dimensions with the construction drawings so the later building application describes the same project.
Can my contractor email a link to the deck plans?
Newmarket asks for unlocked black-and-white PDF drawings through the Development Portal and does not accept file-sharing links. Ask the contractor for the actual PDFs with the issue date in the title block, together with any forms they prepared.
Under section 8 of Ontario’s Building Code Act, obtain the required permit before starting construction or demolition. Permit review considers the Building Code and applicable law, including zoning. Ontario Building Code Act, sections 8 and 10.
Ontario Design Studio prepares building permit drawings for Newmarket. For related design work, see our deck permit drawings. Include your property address and a description of the proposed work when requesting a quote.